Republic Act
Approved June 19, 1965

Republic Act No. 4599

An act to amend section one of republic act numbered sixteen hundred and ten, entitled "an act granting negros electric power corporation a franchise to develop, construct, maintain and operate a hydroelectric power plant in bago river, province of negros occidental"

An Act to Amend Section One of Republic Act Numbered Sixteen Hundred and Ten, Entitled "An Act Granting Negros Electric Power Corporation a Franchise to Develop, Construct, Maintain and Operate a Hydroelectric Power Plant in Bago River, Province of Negros Occidental"

In plain language

This law amends Section 1 of Republic Act No. 1610 to grant the Negros Electric Power Corporation (NEPC) a 25‑year franchise to develop, construct, maintain, and operate a hydroelectric and/or thermal power plant in Negros Occidental, and inserts a new Section 1‑a requiring completion within five years and regulating rates.

  • Amends RA 1610 Section 1 to grant a 25‑year franchise to NEPC
  • Inserts Section 1‑a requiring completion within five years and rate regulation
  • Act takes effect upon approval
energy
electricity
hydroelectric
franchise
Negros Occidental

REPUBLIC ACT No. 4599

An Act to Amend Section One of Republic Act Numbered Sixteen Hundred and Ten, Entitled "An Act Granting Negros Electric Power Corporation a Franchise to Develop, Construct, Maintain and Operate a Hydroelectric Power Plant in Bago River, Province of Negros Occidental"

Be it enacted by the Senate and House of Representatives of the Philippine Congress Assembled:

Section 1

Section one of Republic Act Numbered Sixteen hundred and ten is hereby amended to read as follows:

"Sec. 1. Subject to the provisions of the Constitution and to the terms and conditions established in Act Numbered Thirty-six hundred and thirty-six, as amended, and insofar as the latter law is applicable to, and not inconsistent with this Act, there is hereby granted to Negros Electric Power Corporation, hereinafter known as the grantee, for a period of twenty-five years from the approval of this Act, the right, privilege and authority to develop, construct, maintain and operate a hydroelectric power plant and/or thermal units at suitable places for the purpose of generating and distributing electric lights, heat, and power for sale within the Province of Negros Occidental.

Section 2

The following paragraph to be designated as Section one-a is hereby inserted after Section one of the same Act;

"Sec. 1-a. The grantee shall complete the building of the hydroelectric power plant and/or thermal units herein authorized within five years from the approval of this amendment and charge and collect a schedule of prices and rates for the use of electric current, which schedule of prices and rates shall at all times be subject to regulation by the Public Service Commission.

Section 3

This Act shall take effect upon its approval.

Approved: June 19, 1965.