Article 1723

Chapter 3: Work and Labor · Sec. 1: Household Service (n)

Unamended since 1950

Current text, as of October 24, 2026

The engineer or architect who drew up the plans and specifications for a building is liable for damages if within fifteen years from the completion of the structure, the same should collapse by reason of a defect in those plans and specifications, or due to the defects in the ground. The contractor is likewise responsible for the damages if the edifice falls, within the same period, on account of defects in the construction or the use of materials of inferior quality furnished by him, or due to any violation of the terms of the contract. If the engineer or architect supervises the construction, he shall be solidarily liable with the contractor.

Acceptance of the building, after completion, does not imply waiver of any of the cause of action by reason of any defect mentioned in the preceding paragraph.

The action must be brought within ten years following the collapse of the building. (n)

Consolidated by Alleba from the text of Republic Act No. 386 (Lawphil and the Supreme Court E-Library). Book I provisions on marriage, family relations and parental authority were repealed by the Family Code (Executive Order No. 209, 1987) and are shown for reference only. For information and research only, and not legal advice. For certified copies, refer to the Official Gazette or the issuing agency.